This project included the build-out on the sixth floor of an existing building for a new office and computer lab of approximately 32,056 square feet of which approximately 8,260 square feet is computer lab space. The existing building chilled water systems were used with a new riser directly to the floor. dedicated electrical risers were also utilized from the existing service. The base building VAV systems were used in the office spaces; however, the mechanical and elecrical systems were dedicated to the lab spaces using VAV single zone air-handling units above the ceiling. Much care was taken to maximize ceiling heights. A dedicated control system was also used for the single tenant and tied into the base building systems.
SIGNIFICANT PROJECT FEATURES
COMPLETION DATE September 2017 |